A year after the job, when the extension of time is disputed, the loss and expense claim is being assessed or the defect is being argued over, nobody will remember what happened on the Tuesday of week 36. The site diary will, if it was kept properly. It is the cheapest document on any site and the one that most often decides the money. This article explains why the diary matters, what a daily entry has to record, and the habits that make one stand up.
Why the diary decides claims
Every delay and disruption claim, and every defence to one, turns on contemporaneous records: what was happening on site on the day, recorded on the day by someone who was there. The Society of Construction Law Delay and Disruption Protocol, which is the reference most UK adjudicators, experts and tribunals reach for, puts the keeping of good contemporaneous records at the centre of its guidance, and the reason is simple. A programme analysis produced after the event is only as credible as the facts it is built on, and a witness statement written eighteen months later is memory. A diary entry that says "rain 09:40 to 11:10, drainage D4 to D7 stopped, eleven operatives, 1.5 hours" is evidence.
The contracts point the same way. Under NEC4 a compensation event has to be notified within a time limit and the contractor has to show the effect on the programme; under JCT the contractor has to give notice of delay and provide the particulars. In both cases the question is the same: what happened, when, where, who was affected and for how long. If the diary answers it, the claim has a foundation. If the diary says "wet day, some delays", it does not.
The diary works in the other direction as well. When a subcontractor claims for standing time, the main contractor's diary showing that the crew was redeployed to the roof-light kerbs is the defence. When the client alleges that a defect was caused by workmanship, the diary showing that the hold point was witnessed and passed, with the photograph reference, is the answer.
What a daily entry must record
One page per day, completed at the end of the shift by the person in charge of the site, signed, and never altered afterwards. The headings that turn a diary into a record:
- Header. Project, date and day, project week and day number, site manager, site hours.
- Weather and ground conditions. Morning and afternoon: conditions, temperature, wind speed and gusts, ground state, and the hours lost. The hours lost and the operatives affected are what turn a weather note into a delay record.
- Labour on site by contractor and trade. Company, trade, number, the split where a gang is divided, and the location and activity. A total for the day. This is the entry that proves, or disproves, resource levels a year later.
- Plant on site. Each item with its reference, owner or hire reference, hours worked, hours standing and the operator. Standing hours with the reason are a disruption record in their own right.
- Deliveries. Time, supplier, material and quantity, goods received note reference, and the condition on arrival with the action taken. A damaged unit rejected at the gate with a photograph reference and a nonconformance number is worth more than any later correspondence.
- Visitors. Name, company and role, purpose and outcome, time in and out. The designer's site visit, the client's verbal instruction, the local authority inspection.
- Instructions and information received. From whom, the reference, the subject and the action taken. A verbal instruction goes here on the day and is confirmed in writing; the diary entry is the evidence of when it was given.
- Delays, disruption and events affecting progress. Cause, area and operatives affected, duration, and what was done about it: who was notified, the mitigation, and the reference to the weather record, the nonconformance or the early warning. This is the section a claim or a defence stands on.
- Accidents, near misses and health and safety observations. Type, description and action, reported by whom. Cross-referenced to the incident report where one was raised.
- Quality: inspections, hold points and nonconformities. The ITP line, the level and the attendees, the result and the reference. "ITP E-015 line 2.6, fire-stopping Level 1 zone A, hold point, six penetrations, five passed, one held for re-seal, re-inspect tomorrow" is the kind of entry that ends an argument about whether an inspection took place.
- Progress summary. What was achieved, by area, against the look-ahead; what is behind and why; the hold points booked for tomorrow.
- Photographs taken. The references and what they show, logged on the photographic record.
- Notes for tomorrow. Inspections, permits, deliveries and visitors expected.
- Signature block. Completed by, signature, time, and a weekly review signature by the person the site manager reports to.
The habits that make it stand up
- Same day, every day. A diary written up on Friday for the whole week is not contemporaneous, and an expert will spot the single pen and the identical phrasing. Complete it before leaving site.
- Facts, not opinions. Times, numbers, locations, names and references. "The client's team were unhelpful" is opinion. "Client's representative attended 10:00 to 12:00; instruction to add two double sockets given verbally; confirmed by CVI-011 at 15:00" is fact.
- Cross-reference everything. The weather record, the delivery note, the nonconformance report, the photograph log, the look-ahead, the early warning. The diary is the index; the other records are the detail. A diary that stands alone is weaker than one that points to the evidence.
- Never alter it. If something was wrong, add a dated correction the next day. A diary with entries overwritten is a diary a tribunal will not trust.
- Record the quiet days too. "No delays" on a dry day with full resource is the entry that proves the delay on the wet day was real.
- Keep the numbers honest. Labour and plant figures are checked against the timesheets, the hire invoices and the subcontractor's own records. A diary that inflates them fails the first time it is tested.
- Weekly review. Someone senior reads and signs the week's diary. It catches the missing days, and it means the delays recorded reach the person who has to give the contractual notice.
The diary and the rest of the site records
The diary is not the only daily record, and it should not try to be. Labour returns, plant records, delivery records and weather records each have their own register, and the diary summarises and points to them. Site instructions and confirmations of verbal instruction have their own register. The two-week look-ahead is the plan the diary reports against. The photographic record log gives every photograph a number the diary can cite. When the registers cross-reference each other, a question about any day on the job can be answered in minutes, from documents that agree with each other. When they do not, the claims consultant spends a fortnight reconciling them and the result is still open to challenge.
Word or Excel?
Either works, and a site should use whichever it will actually complete. A Word page per day suits a site that keeps its diary in a folder and signs it. A workbook with one tab per week and one column per day suits a site that keeps its diary at a laptop, and it makes the labour and hours-lost totals add up automatically. The headings should be the same in both so that the record is consistent whichever a site manager uses.
A site diary that cross-references the rest of the site records
The StructAssure Site Management, Planning & Records Pack is 29 documents: the construction phase plan to CDM 2015 with an eleven-page worked example, the two-week look-ahead, the mobilisation checklist, the site diary as a daily Word page and as a weekly Excel workbook with a fully completed worked day, labour, plant, delivery and weather records, site instructions and confirmation of verbal instruction, drawing, RFI and subcontractor registers, the photographic record log, weekly and monthly progress reports, meeting minutes, action log and risk register, all cross-referenced to each other. Native Word and Excel, unlocked, single-company licence. £245.